SRINAGAR: The Divisional Commissioner Kashmir, Pandurang K Pole on Monday chaired 251st High-Level Committee meeting of Circular Road Project Srinagar to review the progress of acquisition cases pertaining to the project.

The meeting deliberated upon acquisition, compensation and rehabilitation of the people whose residential or commercial structures have been acquired by the government to remove bottlenecks on the project.

The meeting also discussed various cases including removal of a bottleneck at Naqashpora junction on western Foreshore Road, expansion of Peer Dastiger Sahib Shrine at Khyanyar, removal of a bottleneck at Shah Mohalla Nawabazar on Syed Mansoor Nawab Bazaar Road, Zewan Junction to Sempora Road widening and other issues of building Community Halls and compensation to structure owners and tenants.

On the occasion, Divisional Commissioner directed SE, Circular Road Project Srinagar, to resolve the issues through negotiations with the parties.

He further ordered him to implement land acquisition law wherever necessary to remove bottlenecks on the Circular Road.

Meanwhile, Pole also interacted with the involved parties in the cases and asked them about their position and opinions regarding their respective issues.

The meeting was attended by DC Srinagar, Dr Shahid Choudhary, ADC Srinagar, SE Circular Road Project, Srinagar, and Engineers of the project besides officers of the revenue department, Srinagar.

LEAVE A REPLY

Please enter your comment!
Please enter your name here