Divisional Commissioner Kashmir, Baseer Ahmad Khan on Tuesday chaired a high level meeting to review the pace of work on prestigious developmental projects in Kashmir including Leh and Kargil districts.

Additional Commissioner Kashmir, Deputy Commissioner Srinagar, VC LAWDA, Chief Engineers of R&B, EM&RE, Systems & Operations & Beacon, Directors from NHAI & NHPC, Officers of Forests & Wild life, Deputy Director Planning, Assistant Commissioner, Traffic advisor, Representatives from RAMKY and other concerned officials were present in the meeting, whereas Deputy Commissioners of valley districts including Kargil & Leh participated in the meeting through video conferencing.

The meeting was informed that the Boulevard road widening project involves 122 kanals of state land and 79 kanals of private land including 17 structures and 20 shops.

On the occasion, Div Com directed the Deputy Commissioner Srinagar to clear all pending land acquisition cases in a time bound manner and disburse the compensation among the affected land and property owners at the earliest so that work on the project is started at an earliest.

He directed the JKTDC, Police, Tourism, LAWDA, SMC & Wild Life Departments to handover land under them which comes under the project to the R&B department within 5 days.

Khan also directed the Engineers of PDD and PHE to take measures for shifting of electric poles and water supply pipes coming under the project immediately.

He also constituted monitoring committee  headed by Deputy Commissioner Srinagar and comprising officers from R&B, PDD, PHE, LAWDA and SMC. The monitoring Committee shall submit the complete report to the Divisional Commissioner’s office within 10 days so that the work can be started immediately on this prestigious project.

The meeting was also informed about the land acquisition process and subsequent compensation to land owners for 61 km long Semi Ring road project. The road starts from Gallandar Pampore to Manigam Ganderbal via Budgam, Srinagar, Baramulla and Bandipora.

Div Com directed the concerned Deputy Commissioners to frame the draft of awards immediately so that the compensation is disbursed to the owners at the earliest.

About the 77 km long NH-444 road project, which starts from Sanzipora Pulwama to Qazigund, it was said that a total of 2000 kanals of land will come under this project sponsored under PMDP. It was said that in a first phase, DPR has been made upto 25 kilometers and poles were erected for demarcation.

Div Com directed Deputy Commissioner Pulwama to complete the revenue papers of first phasewithin 25 days and then submit to Divisional Commissioner’s office for approval and compensation to be disbursed to the owners at earliest.

While reviewing other PMDP projects like AIIMS (which occupies 1772 kanals of land), IIM (which occupies 800 kanals of land), Srinagar-Leh 220 KV transmission line, AMRUT scheme, Rehabilitation of Dal & Nigeen lake dwellers, Transit Camp in Kashmir Division, Neemu Padum Darcha (Kargil), Up-gradation of Srinagar –Uri LOC road, Double Lanning of Srinagar-Leh road (SSG road) via Kargil and Uri-Kaman Post (LOC) and Kishtwar-Simthan Pass-Anantnag road (KSA), Div Com directed concerned Deputy Commissioners and concerned officers to speed up the execution of works so that these prestigious projects are completed within the stipulated time frame.

He also directed the concerned Deputy Commissioners to speed up their efforts so that all bottlenecks on National Highway project and BRO roads are removed so that the work is carried out in a smooth manner.