SRINAGAR: Jammu and Kashmir has 43 national highway projects worth Rs 39,784 crore under execution, while another 11 sanctioned projects involving Rs 9,187 crore are awaiting commencement, the government said on Friday.
A further 31 highway projects, estimated to cost Rs 70,839 crore, are at the detailed project report (DPR) or in-principle approval stage, taking the overall infrastructure portfolio presented by the Public Works Department (PWD) to around Rs 1.28 lakh crore.
These details were presented at a review meeting chaired by Chief Secretary Dr Sajjan Singh Yadav to assess the progress of major road infrastructure projects, development schemes and future connectivity plans across Jammu and Kashmir.
The Additional Chief Secretary, PWD, Anil Kumar Singh, informed the meeting that the Union Territory has a road network of approximately 42,121 kilometres. The infrastructure portfolio includes ongoing and sanctioned works as well as projects at the DPR and in-principle stages.
Reviewing major connectivity projects, the meeting was informed that the Z-Morh Tunnel has been commissioned and is operational, while the Zojila Tunnel achieved its main breakthrough on June 9, 2026, with physical progress reaching 49.64 per cent.
Work on the Vailoo-Donipawa four-laning project has also commenced.
The Srinagar Ring Road Phase-I has achieved around 92 per cent progress, while the tunnels forming part of the Jammu Ring Road have reached approximately 92 per cent completion. The Pulwama Bypass, Sanat Nagar Flyover and Tengpora service road were among the major works reported as completed.
The meeting also reviewed two major tunnel projects sanctioned on NH-244 — the 12.85-km Sudhmahadev-Dranga Tunnel, estimated to cost Rs 4,179.18 crore, and the 38.61-km Singhpora-Vailoo Tunnel, costing Rs 5,600.28 crore. Land acquisition for both projects is under process.
Proposals and progress relating to other strategic connectivity projects, including tunnels at Pir Ki Gali and Sadhna, as well as proposed tunnels in Keran, Machil and Gurez, were also discussed.
On NH-144A, the Akhnoor-Poonch road project being executed under Project SAMPARK has recorded 90.35 per cent length-weighted physical progress. Two of its eight packages have been completed, while work on the remaining six is at different stages.
Under the fourth phase of the Pradhan Mantri Gram Sadak Yojana (PMGSY-IV), 644 roads covering approximately 3,357 kilometres have been sanctioned to connect 789 eligible habitations by March 2028.
The review also covered the financial performance of the department under different funding arrangements. Against the UT Capex allocation of Rs 5,969.55 crore for 2026-27, the government had released Rs 4,061.07 crore, of which Rs 2,142.13 crore had been spent as of November 20, 2026.
Under the Central Road and Infrastructure Fund (CRIF), 294 projects worth Rs 4,337.21 crore have been sanctioned, with 203 completed up to March 2026.
Similarly, 1,074 projects costing Rs 4,967.70 crore have been sanctioned under NABARD’s Rural Infrastructure Development Fund (RIDF), of which 427 had been completed by March 2026.
The department also reported completing 2,046 flood-restoration works between April 1 and October 31, 2026, as part of efforts to restore infrastructure damaged by floods and other disasters.
During April-October this year, 1,500 kilometres of roads were macadamised, 68 identified accident-prone black spots were rectified and 1,265 road safety audits were conducted.
Of the 6,000 migrant transit accommodation units taken up for construction, 5,288 have been completed and handed over to the Department of Disaster Management, Relief, Rehabilitation and Reconstruction.
The Chief Secretary stressed timely completion of projects, construction quality, coordination among departments and effective utilisation of resources. He also called for greater attention to last-mile connectivity in remote, border and hilly areas, emphasising that infrastructure must be capable of withstanding Jammu and Kashmir’s difficult climatic and geological conditions.