SRINAGAR: The Jammu Kashmir and Ladakh High Court has upheld a penalty of Rs 2.5 lakh imposed on Indian Oil Corporation (IOC) for operating a petrol pump in Pulwama without obtaining final access permission from the Highway Administration, while directing the District Magistrate/Deputy Commissioner to examine whether the outlet has fulfilled all statutory requirements and remove highway land encroachments obstructing its access.

Justice Sanjay Dhar, while disposing of a petition filed by Zahida Mushtaq, directed the District Magistrate, Pulwama, to conduct an enquiry into whether the petrol pump, operating under the name and style of M/S Fatima Filling Station at Letpora, had been established at the sanctioned location after obtaining all requisite no-objection certificates (NOCs) from the concerned departments.
The court made it clear that if the petitioner is found to have fulfilled all requirements, she should be allowed to operate the petrol pump. However, if any deficiencies are found, she must be given an opportunity to rectify them, failing which the outlet shall be closed down or sealed.
The judgment, reserved on November 5 and pronounced on November 20, also directed that any encroachments on National Highway land obstructing the construction of access to the petrol pump must be removed in accordance with law. Following construction of the access, the National Highway Authority shall grant the necessary final access permission and allow the outlet to be energised.
The petitioner had approached the High Court challenging a communication dated July 28, 2025, issued by the National Highway Authority, directing the Chief Manager, Retail Sales, of Indian Oil Corporation to deposit a penalty of Rs 2.5 lakh for energising the fuel station at Ch.270+040 (LHS) without obtaining final NOC from the Highway Administration.
The communication had also directed that operations of the retail outlet be de-energised until the final NOC was granted.
According to the petitioner, she had established the fuel station after obtaining the necessary clearances under the Petroleum Act, 1934, and the Petroleum Rules, 2002. She maintained that access permission had also been obtained through Indian Oil Corporation from the National Highway Authority of India on February 25, 2021, for setting up the outlet on land comprising Khasra Nos. 7489, 7190, 7492 and 7493 at Village Letpora, Tehsil Pampore.
She argued that the final access permission could not be secured because of encroachments by shopkeepers and other locals on National Highway land adjoining the petrol pump. Despite repeated representations by her and Indian Oil Corporation, the authorities had failed to remove the encroachments, thereby preventing the construction of the approved access road.
The petitioner contended that she could not be penalised for the authorities’ failure to remove the encroachments and sought directions for the grant of final access permission and removal of illegal occupation of National Highway land under the Control of National Highways (Land and Traffic) Act, 2002.
However, the National Highway Authority defended the penalty, maintaining that the petrol pump had commenced commercial operations without obtaining final access permission, in violation of the Ministry of Road Transport and Highways’ guidelines issued on June 26, 2020.
It submitted that the permission granted to the Indian Oil Corporation was provisional and subject to compliance with prescribed conditions and completion of the approved access and service layer. The authority argued that a petrol pump could not be energised on the basis of provisional permission.
The National Highway Authority also maintained that the petitioner had deposited the penalty on July 31, 2025, and was therefore debarred from challenging the communication.
Meanwhile, respondent No. 12, Zaffar Ahmad Lone, opposed the petition, contending that the petrol pump had been installed in violation of applicable rules and guidelines and without obtaining all requisite NOCs.
He also pointed out that he had earlier filed a separate writ petition, WP(C) No.1919/2025, challenging the installation and operation of the petrol pump. The High Court had disposed of that petition on August 12, 2025, directing the District Magistrate, Pulwama, to examine all requisite NOCs and allow the outlet to operate only if the documents were found complete, valid and effective.
Lone argued that the petitioner had concealed the earlier proceedings while filing the present petition and that the petrol pump was situated less than 50 metres from his residential house. He further claimed that the outlet’s licence had expired on December 31, 2025, without renewal, and that several residential and commercial structures existed in its vicinity.
Rejecting the objection that the present petition was liable to be dismissed for suppression of material facts, Justice Dhar observed that the earlier writ petition did not constitute a material fact whose non-disclosure would disentitle the petitioner from seeking the reliefs claimed in the present proceedings.
The court, however, observed that the petitioner should have brought the earlier order to its notice, particularly while seeking interim relief on September 26, 2025, under which the operation of the petrol pump at the sanctioned location was not to be disturbed.
It noted that the failure to disclose the earlier order had resulted in two apparently conflicting directions, leaving the District Magistrate in a difficult position.
The court observed that the District Magistrate had noticed certain deficiencies in the petitioner’s compliance but was unable to proceed further because of the subsequent interim direction permitting the petrol pump to operate.
Turning to the merits, the High Court examined the Ministry of Road Transport and Highways’ guidelines dated June 26, 2020, governing permission for access to fuel stations and other facilities along National Highways.
Referring to paragraphs 2.3, 2.5.2, 2.6 and 2.11(v) of the guidelines, the court noted that provisional access permission did not authorise a fuel station to commence operations and that energisation was permissible only after the grant of regular access permission.
The guidelines also prescribe a penalty of Rs 2.5 lakh for operating an energised fuel station without obtaining prior permission for access from the Highway Administration.
“The fact that the petitioner has been unable to construct access to her petrol pump for the reasons not attributable to her may offer a justification for her to seek extension of provisional access permission and to pray for further time to construct the access to the petrol pump until the encroachment is removed, but without constructing the access to the petrol pump, the same cannot be energized in any circumstances whatsoever,” the court observed.
Holding that the National Highway Authority was legally justified in imposing the penalty, Justice Dhar upheld the impugned communication dated July 28, 2025.
On the issue of encroachments, the court observed that a series of communications had been addressed by the National Highway Authority and Indian Oil Corporation to the District Administration seeking removal of illegal occupation of National Highway land.
It held that irrespective of whether the encroachments had been made by respondent No. 12 or any other person, they were required to be removed in accordance with the provisions of the Control of National Highways (Land and Traffic) Act, 2002, particularly Chapter IV.
The court pointed out that the District Magistrate is vested with powers under Sections 26, 27, 36 and 43 of the Act to facilitate the removal of encroachments.
Referring to the Supreme Court’s directions in Gyan Prakash v. Union of India, the High Court observed that the District Magistrate, Pulwama, was duty-bound to ensure the removal of encroachments on National Highway land that prevented the construction of access to the petrol pump.
The court clarified that it was not examining the rival claims regarding compliance with the requirements for installation of the petrol pump, as the matter had to be decided by the District Magistrate/Deputy Commissioner in terms of the earlier order dated August 12, 2025.
Accordingly, the writ petition was disposed of with the penalty upheld and directions issued for an enquiry into the petrol pump’s statutory compliance, removal of obstructing encroachments in accordance with law and grant of final access permission upon construction of the required access.
MY Bhat, Senior Advocate, assisted by advocates Shabir Ahmad and Sajid Ahmad, appeared for the petitioner. Advocate Shuja-ul-Haq appeared for respondents 4 and 5, while Senior Advocate NA Beigh, assisted by advocate Sofi Manzoor, represented respondent No. 12. No one appeared for respondents 1 to 3.