SRINAGAR: In what could raise questions on J&K Government’s capacity to harness water resources, the Comptroller and Auditor General of India has revealed that only 10 micro/mini/small hydel power projects with the capacity of 79.75 MWs (five percent) have been commissioned in Jammu & Kashmir against 374 identified project sites with power generation capacity of 1,725.53 MWs.

Follow Us OnG-News | Whatsapp

According to the auditor’s findings on the progress of micro/mini/small hydroelectric projects in Jammu and Kashmir, only 10 projects with a total capacity of 79.75 MWs (five percent) have been commissioned out of the 374 identified project sites capable of generating 1,725.53 MWs. The report further indicates that these projects faced time overruns ranging from four months to over seven years.

“While no action was taken for 225 sites (60 per cent) after their identification, bids were invited for 115 sites (31 per cent) only. No response was received for 70 sites and out of 45 sites awarded for development of hydro power projects, 32 IPPs either failed to fulfil commitments like obtaining statutory clearances for execution of projects or did not deposit upfront premium or the allotment of projects was terminated due to land issues, slow progress and techno economic viability reasons,” reads the report.

The audit also pointed out that Jammu & Kashmir couldn’t avail Rs 2000 crore proposed for the development of small hydroelectric projects under the Prime Minister’s Development Package announced in 2015.

“For 20 sites proposed under Prime Minister’s Development Package (PMDP), GoI had not acceded to the request of the Government of J&K for the release of funds. The project “Implementation of Small Hydro power projects” with provision Rs 2,000 crore was sanctioned (November 2015) under PMDP. The Board of Directors (BoD) of JKPDC in its 73rd meeting (October 2017) accorded approval for implementation of 20 projects through EPC mode to be funded under PMDP as well as funds to be arranged by Power Development Department subject to their viability vis-à-vis evacuation of power. The request of Government of J&K for release of funds under PMDP was not acceded by GoI in view of high project cost and unviable tariff of these 20 projects as a result the JKPDC could not avail assistance from GoI,” the report states.