SRINAGAR: Minister for Public Works, Revenue, Law and Parliamentary Affairs, DMRRR and Elections, Ali Mohammad Sagar, has directed officials to prepare an updated Detailed Project Report (DPR) and a revised phase-wise execution schedule for the new High Court Complex at Rakh-Arth, Bemina, as the project faces a funding requirement of around Rs 290 crore to meet its targeted completion timeline.
During a review of the project at the construction site, the Minister assessed its physical and financial progress and called for closer monitoring, effective coordination among executing agencies and timely availability of funds to prevent delays.
Officials informed him that the project, which began in April 2022, has an approved estimated cost of Rs 908.20 crore, against which Rs 213.50 crore has been spent so far. The main building, estimated to cost around Rs 450 crore, has achieved approximately 65 per cent physical progress. The road component accounts for around Rs 90 crore.
Phase-I of the project is targeted for completion by November 2027, while the first block is expected to be completed within the next six months.
The Minister was informed that the tender for the air-conditioning and heating systems had been allotted, while the electrical works had also been tendered.
Reviewing the financial position, officials said around Rs 290 crore would be required to meet expenditure on the project up to November 2027. The budget provision for 2026-27 includes Rs 87 crore under the Special Assistance to States for Capital Investment (SASCI) and Rs 5.30 crore under the UT Capex. An additional requirement of Rs 41 crore has been proposed under the Budget Estimates for 2027-28.
Sagar directed the concerned officers to reassess the original DPR, taking into account the time elapsed since the project’s commencement, prevailing market rates, technical requirements and the cost implications of the remaining works.
He called for a comprehensive review of the project’s scope, technical specifications and pending components, followed by an updated DPR and a realistic phase-wise execution plan for consideration and approval by the competent authority.
Emphasising the need for proper financial planning, the Minister said timely release of funds and coordination among the executing agencies would be essential to maintain construction progress. He also stressed adherence to technical specifications, construction quality and accountability at every level.
Officials further informed him that Phase-II of the project would be taken up separately through the prescribed tendering process.
The Minister said the new complex should be developed as a modern and fully equipped judicial facility capable of meeting the long-term requirements of the institution.