Rs 901 Cr Contract Moves Srinagar’s Rs 15,000 Crore Satellite Township Closer to Construction

   

SRINAGAR: Srinagar’s proposed Rs 15,000-crore Satellite Township at Rakh Gund Aksha, Bemina, has moved a step closer to implementation, with NBCC (India) Limited awarding a Rs 901.43-crore construction package to Dilip Buildcon Limited for a major group housing complex and allied infrastructure.

Follow Us OnG-News | Whatsapp

Dilip Buildcon disclosed the Letter of Award to the stock exchanges on November 23. The contract covers Satellite Township Phase-I, Package-3, comprising Group Housing-02 and allied works, and will be executed on an Engineering, Procurement and Construction (EPC) basis.

The contract, valued at Rs 901.43 crore including GST, carries a construction timeline of 24 months, followed by two years of operation and maintenance. The award marks the transition of this package from tendering to the contract-award stage, although the company has not specified the date on which construction will commence.

The project is being executed through NBCC, which is developing the satellite township in collaboration with the Srinagar Development Authority (SDA). The two agencies signed a Memorandum of Understanding on August 8, 2024, for the development.

Spread over approximately 406 acres at Rakh Gund Aksha, Bemina, near the proposed Medi City and High Court Complex, the township is among the largest planned urban development initiatives for Srinagar.

NBCC has estimated the overall project cost at approximately Rs 15,000 crore, with implementation envisaged in phases over five years. The corporation has been assigned the responsibility of taking the development from concept to commissioning.

The proposed township is planned as a new urban centre combining residential, commercial, recreational and tourism infrastructure. Its components include serviced residential plots, luxury villas, apartment complexes, commercial office spaces, an indoor sports centre and a 200-key five-star resort.

NBCC has also envisaged sustainability standards for the development, identifying GRIHA or IGBC certification as part of its proposed environmental-performance framework.

The latest contract relates specifically to Group Housing-02. The tender, issued under reference number NBCC/CPG/Bemina/JandK/Pkg-3/2026/588, had an estimated value of approximately Rs 957.62 crore and stipulated a construction period of 720 days.

Dilip Buildcon was declared the lowest bidder for the package on November 11 before NBCC issued the Letter of Award. The final contract value of Rs 901.43 crore is inclusive of GST.

The township’s residential component is being divided into separate procurement packages. A separate tender for Package-2, covering Group Housing-01, was listed at an estimated value of approximately Rs 620.03 crore, also with a 720-day construction period and a two-year maintenance obligation. However, its final award status could not be independently confirmed from the available records.

For Dilip Buildcon, the Srinagar contract adds to its urban infrastructure portfolio and supports its strategy of diversifying beyond road construction into sectors including water, renewable energy and transmission.

The Srinagar award comes against a mixed financial backdrop. Dilip Buildcon’s consolidated revenue declined 20.6 per cent to Rs 8,983.93 crore in FY2025-26. Its profit after tax rose to Rs 1,398.36 crore, although this included exceptional gains of Rs 880.46 crore from subsidiary sales and other items. Working-capital days also increased from 75 to 131.

The satellite township is expected to create a new residential and commercial growth zone in Bemina, an area already witnessing increasing institutional and residential development. Its proximity to the proposed Medi City and High Court Complex places it within an emerging institutional corridor.

The development could expand Srinagar’s planned housing supply and redistribute commercial and institutional activity beyond its existing urban core. Its eventual impact, however, will depend on the delivery of supporting infrastructure, including roads, drainage, water supply, utilities and public services.

With a 24-month construction period and a further two years of maintenance, the package will also test the contractor’s ability to deliver the housing complex within the stipulated timeframe and maintain the completed infrastructure.