KL Report

Srinagar

According to Power Controller, Power Development Department, Kashmir, in order to stabilize and improve Bemina-K.P. Bagh line at Bemina Bye Pass, power supply from the 33 KV line Bemina-K.P. Bagh shall be affected on March 03, 2013 from 10 a.m. to 03 p.m.

Meanwhile, in order to carry out repairing and rectification of damaged 33 KV crossing at chainages 16.950 KM (Harnag), power supply from 33 KV line of Wanpoh-SICOP shall be affected on March 03, 06 and 09, 2013 from 12 p.m. to 02 p.m.
In another communication from the department, in order to carry out reconductoring of 33 KV Rawalpora Air Force Line, power supply from the 33 KV line Rawalpora Air Force line shall be affected on March 04, 06 and 09, 2013 from 10 a.m. to 05 p.m.