by Mehraj Dar
Timely but conditional release of security deposits is essential to accountability in public works, ensuring contractors rectify defects, protect public funds and deliver durable infrastructure across Jammu and Kashmir.

A security deposit in contracts within the Union Territory of Jammu and Kashmir functions as a financial safeguard, ensuring that parties involved in public procurement faithfully fulfil their obligations. Depending on the context — whether large-scale government infrastructure works or goods procurement — the legal framework, calculation methods, and rules governing security deposits vary considerably across sectors. Nevertheless, the core principle behind obtaining security deposits remains the same.
Broadly, security deposits consist of two components: Performance Guarantee and Security Deposit/Retention Money. The Performance Guarantee is obtained from the successful tenderer and amounts to 5 per cent of the accepted tender value, in the form of a CDR/FDR/DD issued by a scheduled bank. Security Deposit/Retention Money, meanwhile, is collected through deductions from contractors’ running account bills at the rate of 10 per cent from each bill.
Both Performance Guarantee and Security Deposit/Retention Money safeguard the client against poor-quality or incomplete work. Across sectors in Jammu and Kashmir, a security deposit is treated strictly as an accessory to the main contract. It bridges trust between contracting entities, provides an immediate source of compensation in the event of default and remains subject to the precise terms outlined in Standard Bidding Documents (SBDs), Notices Inviting Tenders (NITs) or written lease covenants.
Digital Reforms
The online collection and accounting of bid security and performance security have undergone significant changes following recent circular instructions issued by the Finance Department and the introduction of the Pool Account.
Earnest Money Deposit (EMD), or Bid Security, submitted during the initial bidding stage is intended to filter out non-serious participants. The reform process is expected to streamline EMD collection by mandating online cash deposits for EMDs and tender fees and replacing traditional instruments such as Call Deposit Receipts (CDRs) and Bank Guarantees (BGs) with cash deposits.
Unsuccessful bidders receive automated refunds through the system, while the winning bidder’s EMD is retained and adjusted towards the Performance Security.
However, the principal focus of this article is Security Deposit and its release, and the role this process plays in ensuring durable infrastructure and public assets that stand the test of time.

Release Conditions
The release process begins only after the contractor has successfully executed the contract, handed over the completed works or services, and the executing division has certified that no outstanding dues or recovery claims remain.
For performance security deposits, release is strictly contingent upon successful completion of the stipulated Defect Liability Period (DLP), which commonly ranges from six months to several years, depending on the nature of the engineering or infrastructure work. This ensures that structural flaws or defects are rectified at the contractor’s expense.
Upon receipt of the completion certificate and a satisfactory report from the concerned site engineer confirming that no defects remain pending and that all contractual obligations, including warranty obligations, have been fulfilled, the security deposit can be released.
While many contracts specify the DLP as the final milestone for release, the Engineering Manual of the Public Works Department (PWD) in J&K identifies completion of work as the first milestone and the DLP as the final one. Accordingly, some contracts provide for the release of 50 per cent of the security deposit after completion of the work and the remaining 50 per cent after the DLP.
A useful rule for Assistant Accounts Officers, Accounts Officers and Billing Engineers is never to process a retention-money release without written approvals and valid supporting documents. Retention money is the client’s safeguard; releasing it without due diligence can expose the department to financial and legal risks.
The key takeaway is that the release of Security Deposit/Retention Money is not merely a payment exercise. It is the final quality and compliance check of a project. Due diligence and proper documentation are therefore essential to ensuring its smooth closure.
Audit Safeguards
The Central Vigilance Commission (CVC) flags the premature release of security deposits as a potential source of corruption. The Principal Accountant General and the Audit and Inspections Wing of the Finance Department also treat the premature release of security deposits, performance guarantees or earnest money as serious financial irregularities and breaches of public trust.
The CVC explicitly views performance securities and security deposits as essential risk-mitigation instruments. Releasing them before the contractual terms have been fully fulfilled or before the expiry of the Defect Liability Period strips the State of its leverage to penalise defaults or secure rectification of faulty workmanship.
Procedural guidelines stipulate that relaxing conditions or prematurely returning financial guarantees to favour contractors, without fulfilment of the prescribed requirements, creates vulnerabilities to systemic corruption. Such practices also violate the core principles of equitable competition under public procurement frameworks.
Audit paragraphs targeting premature releases can trigger formal inquiries against Executive Engineers and Drawing and Disbursing Officers (DDOs). Financial codes empower audit wings to recommend recovery of equivalent unrecovered amounts directly from the responsible officials if a contractor becomes insolvent or untraceable after premature release.
Quality Assurance
Retaining performance securities throughout the entire Defect Liability Period ensures that contractors remain financially invested in the durability of their projects. Knowing that retention money or bank guarantees remain locked until defects are rectified discourages shortcuts in material quality and structural execution.

In Jammu and Kashmir, infrastructure frequently faces extreme freeze-thaw cycles, heavy snowfall, and flash floods. Strict enforcement ensures that contractors cannot abandon unaddressed structural failures after completing a project. The withheld funds can be deployed directly towards rectifying premature damage.
When structural defects emerge within the warranty period, the defaulting contractor should bear the cost of remedying them entirely through the retained security deposit, rather than drawing fresh funds from the State exchequer.
This approach aims to ensure that rectification costs do not burden the public exchequer and that completed works achieve greater longevity.
Rigid enforcement and rigorous adherence to these provisions can shift the contracting mindset from a transactional race to complete a project towards a lifecycle commitment focused on resilient, high-quality and durable public assets. This is particularly important in view of the challenging topography and harsh climatic conditions of Jammu and Kashmir.
(The author is an Assistant Accounts Officer in the Finance Department. Ideas are personal.)