Srinagar

According to Power Controller Kashmir Province, PDD Bemina, in order to facilitate Project Division Pulwama to construct new 33 kV line for the under construction 10 MVA Receiving Station at Pinglene, shutdown of the 33kV Pampore-Pulwama line shall take place on November 24th and 26th, from 10 AM to 4 PM, affected power supply to the areas being fed by Receiving Stations Newa and Kakpora.

Meanwhile in order to carry out re-conductoring works under DDUGJY, shutdown of 33kV Pampore-B.K Pora and Pampore-Chadoora lines shall take place on November 25, 26, 27, 28, 30, December 01 and 02 from 10 AM to 4:30 PM, affected power supply to the areas being fed by receiving stations B.K Pora, Khanda, Nagam and Charar-i-Sharief on the said dates.