Scheduled Power Shutdown to Affect Multiple Areas Across Kashmir Next Week

   

SRINAGAR: The Kashmir Power Distribution Corporation Limited (KPDCL) has announced a series of scheduled power shutdowns in Srinagar and parts of South Kashmir to facilitate maintenance, infrastructure upgrades, and evacuation of power from the GIS Harwan station.

Follow Us OnG-News | Whatsapp

According to the Chief Engineer, Distribution, KPDCL, the shutdown of the 33KV Burzhama Tap of the 33KV Habak-Zakura-Burzhama line will be observed on May 27, May 29, and June 1. As a result, the 33/11KV Receiving Station at Burzhama will remain off during these dates from 10:00 AM to 04:00 PM, affecting electricity supply to areas including Burzhama, Mulfaq, Gasoo, Chaterhama, Khimber, and nearby localities.

In a separate development, the 33KV Cheshmashahi-BB Cantt Tap line will also undergo shutdown on May 28 from 10:00 AM to 04:30 PM for the maintenance of the overhead Centaur backup line. Power supply to BB Cantt will be affected during this period.

Similarly, the 33KV Badampora-Kurhama line will be shut on May 28 to facilitate repairs on a 33KV isolator and stabilisation works at the Kurhama Receiving Station. The resulting outage will impact supply to the 33/11KV Receiving Stations at Kurhama, Dab, GCET, and Sainik School, thereby affecting Kurhama, Youngpora, Dab, Baroosa, Baba Salina, Wakura, Rabitar, Kondbal, and the surrounding areas.

On May 29, a shutdown is planned on the 33KV Alasteng-Nagbal line for upgradation and stabilisation. This will impact 33/11KV Receiving Stations at Alasteng, Nagbal, Gadoora, and Tulbagh from 10:00 AM to 04:00 PM, affecting power supply in Shuhama, Bakura, Darend, Fatehpora, Chunduna, Shairpathri, Pandach, and other adjoining areas.

Additionally, on the same day, the shutdown of the 33KV Alasteng-Zakura line (under STD-1st) will result in outages at Gulabagh, Ahmad Nagar, and Umarhair Receiving Stations. Consumers in Pathan Colony, Mir Mohalla, 90 Ft Road, Nowbugh, and Khalmullah will experience disruption between 10:00 AM and 04:00 PM.

To facilitate the upgradation of the Wanpoh SICOP line from 0.1 ACSR to 0.2 ACSR, a shutdown has been scheduled for May 28, May 29, and June 2. This will impact 33/11KV Receiving Stations at Shamsipora, SICOP, Zirpara, Veer, and Cheeniwadder. Areas including Jablipora, Srigufwara, and adjacent regions will face outages from 10:00 AM to 05:00 PM on the specified dates.